Workers in Caithness have been praised for their exceptional skills after completing the last section of the longest pipeline bundle which has ever been constructed.
The pipeline which is 3.1 miles long and contains three pipes, was pulled off the beach on January 27 by seven tugs from a 4.3 mile track which streached inland at Wester.
The bundle, which was constructed by the team at Subsea 7 at Wester, was transported to the Andrew Field 140 miles from Aberdeen, where it will be connected to three other bundles to create a 16.8 mile secion of pipework.